Title: | Construction Programmes and Programming: A Critical Review |
Authors: | Olubajo, Oluseun Olukemi Will, Hughes Libby, Schweber |
Keywords: | Delay, Performance, Programme, Schedule, Time, Management, Planning |
Issue Date: | May-2019 |
Publisher: | Emerald Publishing Limited |
Citation: | Olubajo, O., Hughes, W., & Schweber, L. (2019). |
Series/Report no.: | Volume 2; |
Abstract: | Purpose – The purpose of the study is to explore the dominant ideas in research on the management of time in construction. The focus of research has been to improve techniques for optimising the timing and sequence of activities. Design/Methodology/Approach – A critical review of research on construction time management, challenging the typical focus. We examine the assumptions different authors make, underline the limitations of the dominant research approaches and examine the prospects for developing a new approach to researching these issues. Findings – The dominant approach in literature focuses on unique activity traits in construction planning and measurable patterns between time-related variables. This assumes that time in construction can be managed by changing the way activities are calculated. These approaches have not been correlated with improvement in performance. Social practice theory may help to explain how programmes figure as one of many objects used during construction. Research Limitations/Implications – The focus is on reviewing indicative literature from key journals in construction management. The implication is that research is needed about how such documents are used in practice, which goes further than optimising plans in theory. Practical Implications – Future research could focus on understanding the context of construction planning practice and shift the debate from a focus on optimisation to practice. Originality/Value – An interpretivist approach with a focus on how tools such as planning documents are used on site. Social practice theory may provide a clearer explanation of the place of construction planning within the practice of construction management. This could provide solutions that deal effectively with stakeholder expectations around timely completion of construction projects. |
URI: | http://repository.futminna.edu.ng:8080/jspui/handle/123456789/9937 |
ISSN: | 2516-2853 |
Appears in Collections: | Building |
Files in This Item:
File | Description | Size | Format | |
---|---|---|---|---|
Olubajo_ Construction programmes and programming.pdf | 141.35 kB | Adobe PDF | View/Open |
Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.